Show/Hide
Littleton offices and facilities, including Bemis Library, are on a delayed schedule today due to weather conditions. The library and city offices will open at 10 a.m.
Check the map below for current street and utility projects. Some projects may cause traffic delays or detours. Many outdoor project dates are dependent on fair weather. If there are no pins on the map, there are no projects in progress. For details about specific projects, contact the public works department at 303-795-3863.
  • Location East of Jackass Hill Rd
  • Estimated start date mid November 2017
  • Estimated end date end of February 2018

Weekly Newsletters


The Engineering Department staff and our on-site inspector from Merrick are always willing and able to answer any questions you may have during the reconstruction process.

Schedules may change on short notice
Weather, delays by subcontractors, or other unforeseen events can cause schedule changes. The contractor along with the Engineering Department makes every effort to notify residents as soon as possible.

Who to call
Questions regarding the Jackass Gulch Stabilization Project:

  • Carolyn Roan, Littleton Water Resource Manager
    croan@littletongov.org
    303-795-3836
  • Magdiel Garcia. Merrick Engineering (site inspector)
    303-964-3333
  • Rich Borchardt, Urban Drainage and Flood Control District
    303-455-6277
  • Jeron Siegert, ECI Site Construction
    970-342-6127

Other contacts at City of Littleton Public Works Department,
Phone: 303-795-3863

 


 

Jackass Hill Gulch stabilazation project

This is a joint project between the city and Urban Drainage and Flood Control District. Construction work is set to begin the week of November 13 on a portion of Jackass Gulch, a stream that runs on the north side of Mineral Avenue, from the railroad upstream to the Highline Canal. The specific area of construction is located east of Jackass Hill Road.

The project purpose is to stabilize this eroding section that is threatening adjacent homes (along W. Jamison Way) and is also creating excess sediment loads to areas downstream. This is a steep portion of channel with tall, steep, and overhanging banks. The work includes drop structures made of grouted boulders, buried riprap, and revegetation. Trees that must be removed to accommodate the work will be replaced. The trail traffic along Mineral may see temporary disruptions, but no closures are planned at this time.

Return to full list >>

2017 Curb, Gutter and Sidewalk Repair
As part of an annual program, city staff evaluates the condition of existing concrete curb, gutter and sidewalk and develops a list of areas at various locations throughout the city with the highest need of repair or replacement. Work is expected to take place from mid-June through mid-August. Drivers and/or pedestrians may encounter temporary lane or sidewalk restrictions during construction. Parking in the immediate vicinity may be restricted during construction.