Public Works Projects

Print
Press Enter to show all options, press Tab go to next option

Check the list below for current street and utility projects. Some projects may cause traffic delays or detours. Many outdoor project dates are dependent on fair weather. For more information about specific projects, contact the public works department at 303-795-3863.

Project Location
Anticipated Start Date
2018 Mill & Overlay Project*
Two segments of W. Long Circle south of W. Long Drive
Late August
2018 Mill & Overlay Project*
Windermere St. from Belleview Ave. to Littleton Blvd. Late August
2018 Chip Seal Project*
Prince St., Centennial Dr., and Prentice Ave. Mid August
2018 Chip Seal Project*
Prince St. from Ridge Rd. to Jackass Hill Rd.
Mid August
Sanitary & Storm Sewer Inspection Program Various locations throughout the city Mid Summer
2018 Crack Seal Projects
Various locations throughout the city
Completed
Bowles/Federal Intersection Safety Improvements
W. Bowles Ave. at S. Federal Blvd.
TBD
Federal/Berry Pedestrian Signal
S. Federal Blvd. at Berry Ave.
TBD

Our TABOR tax dollars at work. Thank you Littleton votors.*The Chip Seal and Mill & Overlay projects are being paid for with excess TABOR funds. Thank you Littleton voters!

  

Projects at other agencies:

   

Did you know?

Reconstruction of a street costs $1.3 million per mile, while road preservation methods such as crack sealing and mill and overlay cost as little as $5,500 per mile? Street Maintenance Project Costs

   

Public Works News: