1. Submit (2) two sets of gas pipe isometric drawings.

2. Indicate amount of BTU's being served.

3. Type of material being used, polyethylene, PS-2, schedule 40 steel, CSST, etc.

4. Size of pipe %2, 3/4, 1" etc.

5. If polyethylene is being used, have a note on diagram or gas pipe isometric drawing of a tracer 18 AWG approved for burial wire in trench.

6. The depth of trench.

7. Location of shut-off values.

The pressure test is one and a half times the proposed working pressure, but not less than 3 psig. Test duration is 10 minutes.